Plumbing Code (Part 10) | Master Plumber Licensure Exam Refresher

Share

Summary

This video, "Plumbing Code (Part 10) | Master Plumber Licensure Exam Refresher," provides a concise review of plumbing codes essential for the Master Plumber Licensure Exam. It covers various topics from pipe support and backfilling trenches to specific regulations for sacariums, pipe materials, and septic tanks.

Highlights

Blank Flange and Reduced Pressure Principle Backflow Assembly
00:02:21

A blank flange is a pipe flange not drilled for bolt holes. A Reduced Pressure Principle (RPP) backflow assembly consists of two independently acting, internally loaded check valves, a differential pressure relief valve, four properly located tests, and two isolation gate valves.

Plastic Pipe Support and Trench Backfill
00:00:09

Plastic pipes must be supported at every 1-meter interval. Trenches should be backfilled with thin layers of clean earth, free from stones, boulders, cinders, or other corrosive materials.

Sacrarium Connections and Galvanized Pipe Usage
00:01:04

Sacrarium cups, sinks at church altars, and baptistery outlets must discharge directly to the ground and not connect to the sanitary drainage system. Galvanized wrought iron or steel pipes should not be used underground and must be kept at least 152 mm above ground.

Vertical Piping Shapes and Fixture Supply Exposed Pipes
00:01:46

Vertical piping can be round, square, or rectangular. Fixture supply pipings are exposed for faculty and maintenance.

Cast Iron Pipe Support and Trench Clearance
00:03:04

Cast iron pipe stacks must be supported at their base and on each floor. The bottom of pipe trenches deeper than an adjacent building's footing and parallel to it must be at least 45 degrees away.

Distribution Drain Line Spacing and Holy Water Disposal
00:03:39

Distribution drain lines and leaching beds should be more than 1.8 meters apart on centers. Waste from holy water and wash water at church altar services must be disposed of directly into the ground, not the sanitary drainage system. No fixture shall be double trapped.

Septic Tank Cover Requirements and Plumbing Documentation
00:04:35

Septic tank covers must be structurally designed to withstand earth loads and support an earth load of not less than 14.4 kPa when maximum coverage does not exceed 0.9 meters. All necessary requirements, including plans and specifications, should be submitted in six sets.

Plumbing Permit Validity and Inspection Requests
00:05:25

A plumbing permit becomes null and void if work is suspended and abandoned after 120 days from commencement. Inspection requests to the administrative authority must be filed at least three days before the intended inspection date.

Public Space Definition and Manhole Purpose
00:06:06

An alley is defined as any public space, public park, or thoroughfare between 2 and 3 meters in width dedicated for public use. A manhole is a large opening in a sewer line or plumbing system, sized for a person to gain access for maintenance.

Pipe Protection from Corrosion
00:06:52

All pipes passing through or under cinders or other corrosive materials must be protected from external corrosion by encasing them with a polyethylene sheath.

Recently Summarized Articles

Loading...